Infrakey Waco Data Park Gas 2
BetaActiveGas - Combustion (gas) TurbineERCOTLive · ERCOT
— generation in McLennan, Texas · In queue since April 2025 · Proposed COD June 2027
—
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 2m
Pre-Study0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
Texas
County
McLennan
Region
ERCOT
Developer
Infrakey Capital LLC
Utility
—
Entity
ERCOT
Point of Interconnection
252 BOSQUESW8 138kV (Brazos Connection)
Data Source
Live · ERCOT
No news available for this project.