Obbligato BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
200.71 MW storage in Milam, Texas · In queue since June 2025 · Proposed COD February 2029
200.71 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryJun 19, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-28
Project Details
State
Texas
County
Milam
Region
ERCOT
Developer
Obbligato BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 120# TALBRTRIDG – 3683# MINERVA1_8
Data Source
Live · ERCOT