Metro BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
200.71 MW storage in Caldwell, Texas · In queue since February 2025 · Proposed COD December 2030
200.71 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 10m
Pre-Study0%
Queue EntryFeb 25, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-07
Project Details
State
Texas
County
Caldwell
Region
ERCOT
Developer
Metro BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138 kV LYTTON8 (9075)
Data Source
Live · ERCOT
No news available for this project.