Fivemile Wind — Project Summary

Queue ID
ERCOT-27INR0474
Capacity
282.3 MW
Technology
Wind
Status
active
Location
Dawson, Texas
Region
ERCOT
Developer
Longview Wind, LLC
IA Status

Fivemile Wind

BetaActiveWind - Wind TurbineERCOTLive · ERCOT

282.3 MW generation in Dawson, Texas · In queue since April 2025 · Proposed COD November 2028

282.3 MW

Capacity

0

Components

11 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryApr 25, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

Project Details

State

Texas

County

Dawson

Region

ERCOT

Developer

Longview Wind, LLC

Utility

Entity

ERCOT

Point of Interconnection

To 138 kV Hardy Morgan substation (Bus # 11363)

Data Source

Live · ERCOT

No news available for this project.