Roboman Solar
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
272.6 MW generation in Coke, Texas · In queue since July 2025 · Proposed COD July 2029
272.6 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryJul 7, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
Texas
County
Coke
Region
ERCOT
Developer
Roboman Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV (#76009) Twin Buttes – (#76090) Divide Ckt 1
Data Source
Live · ERCOT
No news available for this project.