Dairyland Storage
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
301.8 MW storage in Hopkins, Texas · In queue since April 2025 · Proposed COD April 2029
301.8 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryApr 21, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-30
Project Details
State
Texas
County
Hopkins
Region
ERCOT
Developer
ENGIE IR Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
To 345 kV Birthright Station (#11684)
Data Source
Live · ERCOT