Gulf Prairie Solar — Project Summary

Queue ID
ERCOT-27INR0449
Capacity
202.17 MW
Technology
Solar
Status
active
Location
Brazoria, Texas
Region
ERCOT
Developer
Gulf Prairie Energy LLC
IA Status

Gulf Prairie Solar

BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT

202.17 MW generation in Brazoria, Texas · In queue since June 2025 · Proposed COD December 2028

202.17 MW

Capacity

0

Components

9 months

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntryJun 19, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

Texas

County

Brazoria

Region

ERCOT

Developer

Gulf Prairie Energy LLC

Utility

Entity

ERCOT

Point of Interconnection

(CEHESub) looped either 1) on 138 kV circuit 82 between RIWOOD (#43150) and Angleton (#42110), or 2) on 345 kV circuit 18 between DOW (#42500) and Huizache (#46640)

Data Source

Live · ERCOT

No news available for this project.