Moon Chapel Wind
BetaActiveWind - Wind TurbineERCOTLive · ERCOT
379.2 MW generation in Tom Green, Texas · In queue since February 2025 · Proposed COD October 2028
379.2 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryFeb 14, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-01
Project Details
State
Texas
County
Tom Green
Region
ERCOT
Developer
Orsted Onshore Development North America, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 76090 Divide - 76009 Twin Buttes Ckt 1
Data Source
Live · ERCOT
No news available for this project.