Diamond Sage BESS 2
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
100.14 MW storage in Webb, Texas · In queue since January 2025 · Proposed COD October 2028
100.14 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-01
Project Details
State
Texas
County
Webb
Region
ERCOT
Developer
DGC Renewables, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709)
Data Source
Live · ERCOT