Serenity Wind
473 MW generation in Armstrong, Texas · In queue since March 2025 · Proposed COD September 2028
473 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-18
State
Texas
County
Armstrong
Region
ERCOT
Developer
Serenity Wind, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
23931 MIDPOINT SWITCH 345 kV
Data Source
Live · ERCOT
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
Wind power is the second largest source of energy in Brazil. As of this past summer the country has around 7000 wind turbines.
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
Wind power is the second largest source of energy in Brazil. As of this past summer the country has around 7000 wind turbines.
Last updated 2026-03-26