Wisdom Solar SLF
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
299.37 MW generation in Pecos, Texas · In queue since February 2025 · Proposed COD October 2027
299.37 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 8m
Pre-Study0%
Queue EntryFeb 12, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-06
Project Details
State
Texas
County
Pecos
Region
ERCOT
Developer
Wisdom Green Energy LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV #38455 HOLIDAY SUB TNP - #38450 SOAPTREE TNP
Data Source
Live · ERCOT