Clairemont Solar 1
ERCOT-27INR0435BetaActiveSolarPhotovoltaic SolarERCOTLive · ERCOT
251.75 MW generation in Kent, TX · In queue since January 2025 · Proposed COD February 2029
251.75 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Signed Nov 2025
Interconnection Timeline
Queue → IA
10 months
IA → COD
3y 3m
Total Duration
10 months
Construction0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 24, 2025
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2029-02-13
Project Details
State
TX
County
Kent
Region
ERCOT
Developer
Clairemont Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59908 Novaprime 345kV
Data Source
Live · ERCOT
No news available for this project.