Jourdanton BESS — Project Summary

Queue ID
ERCOT-27INR0433
Capacity
9.82 MW
Technology
Battery
Status
active
Location
Atascosa, TX
Region
ERCOT
Developer
Jourdanton BESS LLC
IA Status
In Progress (unknown study)

Jourdanton BESS

BetaActiveBatteryERCOTLBNL

9.82 MW storage in Atascosa, TX · In queue since November 2024 · Proposed COD December 2025

9.82 MW

Capacity

1

Components

Battery

1y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 1m

Schedule

3 months past proposed COD

In Study38%
Queue EntryNov 7, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

TX

County

Atascosa

Region

ERCOT

Developer

Jourdanton BESS LLC

Utility

Entity

ERCOT

Data Source

LBNL

No news available for this project.