Bluebonnet Trail Solar
BetaActiveSolarERCOTLBNL + Live
150.7 MW generation in Ellis, TX · In queue since December 2024 · Proposed COD September 2028
150.7 MW
Capacity
1
Components
Solar
1y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntryDec 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-19
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
Bluebonnet trail solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5
Data Source
LBNL + Live