Edgewood BESS 2 — Project Summary

Queue ID
ERCOT-27INR0413
Capacity
102.1 MW
Technology
Battery
Status
active
Location
Van Zandt, Texas
Region
ERCOT
Developer
Tempus Power management LLC
IA Status

Edgewood BESS 2

BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT

102.1 MW storage in Van Zandt, Texas · In queue since January 2025 · Proposed COD March 2028

102.1 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 2m

Pre-Study0%
Queue EntryJan 28, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-01

Project Details

State

Texas

County

Van Zandt

Region

ERCOT

Developer

Tempus Power management LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap Edgewood 138kV bus(3181) to 3174

Data Source

Live · ERCOT

No news available for this project.