Reforzar BESS 1 — Project Summary

Queue ID
ERCOT-27INR0400
Capacity
200.6 MW
Technology
Battery
Status
active
Location
Brooks, TX
Region
ERCOT
Developer
Tempus Power management LLC
IA Status
Facility Study

Reforzar BESS 1

BetaActiveBatteryERCOTLBNL + Live

200.6 MW storage in Brooks, TX · In queue since December 2024 · Proposed COD April 2028

200.6 MW

Capacity

1

Components

Battery

1y 3m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 4m

Facilities Study50%
Queue EntryDec 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-13

Project Details

State

TX

County

Brooks

Region

ERCOT

Developer

Tempus Power management LLC

Utility

Entity

ERCOT

Point of Interconnection

POIB is AEP's new Reforzar 345kV switching station, PSSE bus number 80078

Data Source

LBNL + Live

No news available for this project.