Zodiac Storage
BetaActiveBatteryERCOTLBNL + Live
125.58 MW storage in Val Verde, TX · In queue since November 2024 · Proposed COD August 2028
125.58 MW
Capacity
1
Components
Battery
1y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 9m
Facilities Study50%
Queue EntryNov 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-29
Project Details
State
TX
County
Val Verde
Region
ERCOT
Developer
Grenergy USA
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 8680 RGEC Rough Canyon (ROUGHCAN4A) - 8683 Comstock (COMSTOCK4A) Line
Data Source
LBNL + Live
No news available for this project.