Sugaree Solar
ERCOT-27INR0389BetaActiveSolarERCOTLBNL + Live
251.4 MW generation in Maverick, TX · In queue since October 2024 · Proposed COD September 2028
251.4 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryOct 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-21
Project Details
State
TX
County
Maverick
Region
ERCOT
Developer
Sugaree Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV Escondido (8260) to Brackettville (8252)
Data Source
LBNL + Live
No news available for this project.