Windjammer Windpower
ERCOT-27INR0383BetaActiveWindERCOTLBNL + Live
292.58 MW generation in Glasscock, TX · In queue since September 2024 · Proposed COD December 2028
292.58 MW
Capacity
1
Components
Wind
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntrySep 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
Windjammer Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 59902 Sand Bluff Wind Farm - 59907 Bernoulli
Data Source
LBNL + Live