Buck Ranch Storage SLF
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
40.8 MW storage in Live Oak, Texas · In queue since January 2025 · Proposed COD August 2028
40.8 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 7m
Pre-Study0%
Queue EntryJan 28, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-08-09
Project Details
State
Texas
County
Live Oak
Region
ERCOT
Developer
Buck Ranch Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5690 WEST GEORGE WEST SUB 69kV
Data Source
Live · ERCOT