Feather Dalea BESS
BetaActiveBatteryERCOTLBNL + Live
200 MW storage in Glasscock, TX · In queue since October 2024 · Proposed COD July 2027
200 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 9m
Facilities Study50%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-02
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
RWE Clean Energy Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
59902 Sand_Bluff 345kV
Data Source
LBNL + Live
No news available for this project.