Gold Coin Storage
BetaActiveBatteryERCOTLBNL
72.95 MW storage in Montague, TX · In queue since November 2024 · Proposed COD July 2027
72.95 MW
Capacity
1
Components
Battery
1y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 8m
Facilities Study50%
Queue EntryNov 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Montague
Region
ERCOT
Developer
Grenergy USA
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1470 Newport - 616 Carter
Data Source
LBNL
No news available for this project.