Gardner Draw Solar
ERCOT-27INR0355BetaActiveSolarERCOTLBNL + Live
200 MW generation in Glasscock, TX · In queue since October 2024 · Proposed COD December 2027
200 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Facilities Study50%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
RWE Clean Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59902 Sand Bluff 345kV
Data Source
LBNL + Live