Saddle Horn Station BESS SLF
BetaActiveBatteryERCOTLBNL + Live
177.41 MW storage in Comanche, TX · In queue since September 2024 · Proposed COD September 2028
177.41 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Facilities Study50%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-11
Project Details
State
TX
County
Comanche
Region
ERCOT
Developer
Saddle Horn Station BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 1650 COMANCHE_T8 - 290SHILOHC
Data Source
LBNL + Live
No news available for this project.