Johnson Grass Solar
BetaActiveSolarERCOTLBNL + Live
195.8 MW generation in Mitchell, TX · In queue since October 2024 · Proposed COD April 2028
195.8 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 6m
Facilities Study50%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-19
Project Details
State
TX
County
Mitchell
Region
ERCOT
Developer
Johnson Grass Solar ,LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV (#11395) Navigation - (#10054) Cattlemen
Data Source
LBNL + Live