Dorsey Road BESS
BetaActiveOther - Battery Energy StorageERCOTLive · ERCOT
155 MW storage in Bexar, Texas · In queue since March 2025 · Proposed COD August 2029
155 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 5m
Pre-Study0%
Queue EntryMar 6, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-08-31
Project Details
State
Texas
County
Bexar
Region
ERCOT
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV Chavanea (5085) - Palo Alto (5330).
Data Source
Live · ERCOT
No news available for this project.