Sentinel Solar
BetaActiveSolarERCOTLBNL
271.3 MW generation in La Salle, TX · In queue since October 2024 · Proposed COD January 2029
271.3 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryOct 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-24
Project Details
State
TX
County
La Salle
Region
ERCOT
Developer
Alamo Ranch Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 80219 Lobo - 5709 Fowlerton CKT2
Data Source
LBNL
No news available for this project.