Rock Island Generating (TEF -Due Diligence) — Project Summary

Queue ID
ERCOT-27INR0321
Capacity
121.8 MW
Technology
Gas
Status
active
Location
Colorado, TX
Region
ERCOT
Developer
Kerrville Public Utility Board Public Facility Corporation
IA Status
Facility Study

Rock Island Generating (TEF -Due Diligence)

ERCOT-27INR0321BetaActiveGasERCOTLBNL + Live

121.8 MW generation in Colorado, TX · In queue since July 2024 · Proposed COD June 2027

121.8 MW

Capacity

1

Components

Gas

1y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 11m

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

TX

County

Colorado

Region

ERCOT

Developer

Kerrville Public Utility Board Public Facility Corporation

Utility

Entity

ERCOT

Service Type

Point of Interconnection

57640 Rock Island 138 kV

Data Source

LBNL + Live

No news available for this project.