Spindletop Storage
ERCOT-27INR0314BetaActiveBatteryERCOTLBNL + Live
142.57 MW storage in Nacogdoches, TX · In queue since July 2024 · Proposed COD June 2027
142.57 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 11m
Facilities Study50%
Queue EntryJul 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Nacogdoches
Region
ERCOT
Developer
Banita Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3109 Stryker - 3117 Lufkin
Data Source
LBNL + Live
No news available for this project.