Spindletop Solar — Project Summary

Queue ID
ERCOT-27INR0313
Capacity
286.04 MW
Technology
Solar
Status
active
Location
Nacogdoches, TX
Region
ERCOT
Developer
Banita Creek Solar LLC
IA Status
Facility Study

Spindletop Solar

ERCOT-27INR0313BetaActiveSolarERCOTLBNL + Live

286.04 MW generation in Nacogdoches, TX · In queue since July 2024 · Proposed COD December 2027

286.04 MW

Capacity

1

Components

Solar

1y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 5m

Facilities Study50%
Queue EntryJul 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-29

Project Details

State

TX

County

Nacogdoches

Region

ERCOT

Developer

Banita Creek Solar LLC

Utility

Entity

ERCOT

Service Type

Data Source

LBNL + Live

No news available for this project.