Please change project entity from Pronghorn Storage, LLC to Beaverhead Solar, LLC. — Project Summary

Queue ID
ERCOT-27INR0308
Capacity
61.5 MW
Technology
Battery
Status
active
Location
Jim Wells, TX
Region
ERCOT
Developer
Pronghorn Storage, LLC
IA Status
Facility Study

Please change project entity from Pronghorn Storage, LLC to Beaverhead Solar, LLC.

BetaActiveBatteryERCOTLBNL + Live

61.5 MW storage in Jim Wells, TX · In queue since August 2024 · Proposed COD July 2027

61.5 MW

Capacity

1

Components

Battery

1y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

2y 11m

Facilities Study50%
Queue EntryAug 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-31

Project Details

State

TX

County

Jim Wells

Region

ERCOT

Developer

Pronghorn Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

Direct to Sub 69kv #5653 Ben Bolt.

Data Source

LBNL + Live

No news available for this project.