Fletcher BESS — Project Summary

Queue ID
ERCOT-27INR0304
Capacity
309.92 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Archer Energy Center, LLC
IA Status
Facility Study

Fletcher BESS

BetaActiveBatteryERCOTLBNL

309.92 MW storage in Harris, TX · In queue since July 2024 · Proposed COD July 2027

309.92 MW

Capacity

1

Components

Battery

1y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3 years

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-02

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Archer Energy Center, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138 kV 44630 Garth _x0013_ 48156 Highlands

Data Source

LBNL

No news available for this project.