Symank Solar
BetaActiveSolarERCOTLBNL + Live
66.55 MW generation in Bosque, TX · In queue since November 2024 · Proposed COD December 2027
66.55 MW
Capacity
1
Components
Solar
1y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
Facilities Study50%
Queue EntryNov 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-15
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
BT Symank Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69 kV 37470 TNOLSEN - 37520 TNSYCAMORE
Data Source
LBNL + Live
No news available for this project.