Tolivar Power Plant (TEF- Due Diligence)
ERCOT-27INR0297BetaActiveGasERCOTLBNL + Live
225.6 MW generation in Reeves, TX · In queue since July 2024 · Proposed COD May 2027
225.6 MW
Capacity
1
Components
Gas
1y 9m
In Queue
IA Executed
IA Status
Signed Nov 2024
Interconnection Timeline
Queue → IA
4 months
IA → COD
2y 6m
Total Duration
4 months
Construction75%
Queue EntryJul 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 12, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2027-05-06
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
Pecos Power Plant, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV 38045 IH20-38043 COWPEN
Data Source
LBNL + Live