Tolivar Power Plant (TEF- Due Diligence) — Project Summary

Queue ID
ERCOT-27INR0297
Capacity
225.6 MW
Technology
Gas
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Pecos Power Plant, LLC
IA Status
IA Executed

Tolivar Power Plant (TEF- Due Diligence)

ERCOT-27INR0297BetaActiveGasERCOTLBNL + Live

225.6 MW generation in Reeves, TX · In queue since July 2024 · Proposed COD May 2027

225.6 MW

Capacity

1

Components

Gas

1y 9m

In Queue

IA Executed

IA Status

Signed Nov 2024

Interconnection Timeline

Queue → IA

4 months

IA → COD

2y 6m

Total Duration

4 months

Construction75%
Queue EntryJul 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 12, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2027-05-06

Project Details

State

TX

County

Reeves

Region

ERCOT

Developer

Pecos Power Plant, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 KV 38045 IH20-38043 COWPEN

Data Source

LBNL + Live

No news available for this project.