Sugar Land Power Plant
BetaActiveGasERCOTLBNL
147.6 MW generation in Fort Bend, TX · In queue since August 2024 · Proposed COD October 2027
147.6 MW
Capacity
1
Components
Gas
1y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Facilities Study50%
Queue EntryAug 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Fort Bend
Region
ERCOT
Developer
Imperial Power Plant, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 44015 W A Parish - 44671 Stafford CKT 9
Data Source
LBNL
No news available for this project.