Rain Lily Solar 1
BetaActiveSolar - Photovoltaic SolarERCOTLive · ERCOT
147.76 MW generation in Hood, Texas · In queue since February 2025 · Proposed COD October 2028
147.76 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryFeb 25, 2025
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-10-15
Project Details
State
Texas
County
Hood
Region
ERCOT
Developer
Rain Lily Solar 1 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV #350 ABBYBEND - #363 HOOD
Data Source
Live · ERCOT
No news available for this project.