EMPower Odessa
BetaActiveGasERCOTLBNL + Live
123.4 MW generation in Ector, TX · In queue since July 2024 · Proposed COD March 2028
123.4 MW
Capacity
1
Components
Gas
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
3y 8m
Facilities Study50%
Queue EntryJul 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-09
Project Details
State
TX
County
Ector
Region
ERCOT
Developer
EMPOWER TXMX
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138 kV 1110 EDWARDS TAP - 1102 JUDKINS
Data Source
LBNL + Live
No news available for this project.