Paddlewheel BESS SLF — Project Summary

Queue ID
ERCOT-27INR0256
Capacity
50 MW
Technology
Battery
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
Paddlewheel Solar, LLC
IA Status
Facility Study

Paddlewheel BESS SLF

BetaActiveBatteryERCOTLBNL

50 MW storage in Matagorda, TX · In queue since June 2024 · Proposed COD September 2027

50 MW

Capacity

1

Components

Battery

1y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Facilities Study50%
Queue EntryJun 3, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-30

Project Details

State

TX

County

Matagorda

Region

ERCOT

Developer

Paddlewheel Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

138 kV Pavlov Station (#8608); AEP

Data Source

LBNL

No news available for this project.