Sayle Solar
BetaActiveSolarERCOTLBNL + Live
122.4 MW generation in Jackson, TX · In queue since June 2024 · Proposed COD May 2027
122.4 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
2y 11m
Facilities Study50%
Queue EntryJun 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-31
Project Details
State
TX
County
Jackson
Region
ERCOT
Developer
Sayle Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69kV #5522 Edna - #5518 El Toro SW
Data Source
LBNL + Live