Brookview Road BESS — Project Summary

Queue ID
ERCOT-27INR0243
Capacity
203.2 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Brookview Reliability Project LLC
IA Status
Facility Study

Brookview Road BESS

ERCOT-27INR0243BetaActiveBatteryERCOTLBNL + Live

203.2 MW storage in Harris, TX · In queue since April 2024 · Proposed COD May 2028

203.2 MW

Capacity

1

Components

Battery

2 years

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Facilities Study50%
Queue EntryApr 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-02

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Brookview Reliability Project LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Channelview 1 ( 40280) 138kV Substation

Data Source

LBNL + Live

No news available for this project.