Callan Solar
BetaActiveSolarERCOTLBNL + Live
90.97 MW generation in Menard, TX · In queue since June 2024 · Proposed COD September 2028
90.97 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 3m
Facilities Study50%
Queue EntryJun 13, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-01
Project Details
State
TX
County
Menard
Region
ERCOT
Developer
Menard PV, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 69kV 60386 Heartland to 6363 Yellow Jacket
Data Source
LBNL + Live