Ochoa Energy Storage II
BetaActiveBatteryERCOTLBNL + Live
501.72 MW storage in Waller, TX · In queue since April 2024 · Proposed COD January 2029
501.72 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntryApr 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
TX
County
Waller
Region
ERCOT
Developer
Ochoa Energy Storage II LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 44420 Katy - 44230 Flewellen
Data Source
LBNL + Live
No news available for this project.