PALO VERDE BESS
BetaActiveBatteryERCOTLBNL + Live
150 MW storage in San Patricio, TX · In queue since April 2024 · Proposed COD September 2027
150 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Facilities Study50%
Queue EntryApr 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-02
Project Details
State
TX
County
San Patricio
Region
ERCOT
Developer
RWE Clean Energy Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 8624 Grissom _x0013_ 8455 Lon C Hill
Data Source
LBNL + Live
No news available for this project.