Benitoite Storage
BetaActiveBatteryERCOTLBNL + Live
125.65 MW storage in Van Zandt, TX · In queue since March 2024 · Proposed COD August 2027
125.65 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 5m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-25
Project Details
State
TX
County
Van Zandt
Region
ERCOT
Developer
BT Van Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 3183 VAN_8 - 3197 TYLERSW_8
Data Source
LBNL + Live