Fierce River Solar
BetaActiveSolarERCOTLBNL
895.67 MW generation in Starr, TX · In queue since March 2024 · Proposed COD December 2028
895.67 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-06
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
Rio Grande Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 80355 Del Sol - 80119 Frontera Ckt 1
Data Source
LBNL
No news available for this project.