Donna Solar
BetaActiveSolarERCOTLBNL + Live
168.97 MW generation in Hidalgo, TX · In queue since March 2024 · Proposed COD February 2029
168.97 MW
Capacity
1
Components
Solar
2 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryMar 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-22
Project Details
State
TX
County
Hidalgo
Region
ERCOT
Developer
Donna Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV (80137) Stewart Road - (8383) North Edinburg CKT ID#01
Data Source
LBNL + Live