Dunlay Solar — Project Summary

Queue ID
ERCOT-27INR0203
Capacity
150.5 MW
Technology
Solar
Status
active
Location
Medina, TX
Region
ERCOT
Developer
Medina PV, LLC
IA Status
Facility Study

Dunlay Solar

BetaActiveSolarERCOTLBNL + Live

150.5 MW generation in Medina, TX · In queue since March 2024 · Proposed COD June 2028

150.5 MW

Capacity

1

Components

Solar

2 years

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

TX

County

Medina

Region

ERCOT

Developer

Medina PV, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 5813 PearsonSW - 5225 Hondo

Data Source

LBNL + Live

No news available for this project.