Shallow Valley Storage — Project Summary

Queue ID
ERCOT-27INR0202
Capacity
103.39 MW
Technology
Battery
Status
active
Location
Ward, TX
Region
ERCOT
Developer
Shallow Valley Storage, LLC
IA Status
Facility Study

Shallow Valley Storage

BetaActiveBatteryERCOTLBNL + Live

103.39 MW storage in Ward, TX · In queue since July 2024 · Proposed COD June 2028

103.39 MW

Capacity

1

Components

Battery

1y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 11m

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

TX

County

Ward

Region

ERCOT

Developer

Shallow Valley Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub

Data Source

LBNL + Live