CORRUSCANT BESS
BetaActiveBatteryERCOTLBNL + Live
337.35 MW storage in Dickens, TX · In queue since February 2024 · Proposed COD April 2027
337.35 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
Facilities Study50%
Queue EntryFeb 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-18
Project Details
State
TX
County
Dickens
Region
ERCOT
Developer
AEU Battery Project III LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A
Data Source
LBNL + Live
No news available for this project.