Cedar Draw BESS — Project Summary

Queue ID
ERCOT-27INR0193
Capacity
225.7 MW
Technology
Battery
Status
active
Location
Scurry, TX
Region
ERCOT
Developer
Cedar Draw Solar LLC
IA Status
Facility Study

Cedar Draw BESS

BetaActiveBatteryERCOTLBNL + Live

225.7 MW storage in Scurry, TX · In queue since March 2024 · Proposed COD December 2027

225.7 MW

Capacity

1

Components

Battery

2 years

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 9m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

TX

County

Scurry

Region

ERCOT

Developer

Cedar Draw Solar LLC

Utility

Entity

ERCOT

Point of Interconnection

60011 Nebula7A 345kV

Data Source

LBNL + Live